Launch Countdown
Flight Activity Menu Main Menu Search Media Contacts

DATE      TIME (EST) MET EVENT
12/02/98   7:09:00 PM T - 000/06:00:00 THE COUNT HAS RESUMED

********************************
* NOTE: THE NEXT PLANNED HOLD *
* IS AT T-03H00M *
********************************
THIS IS THE RE-ENTRY POINT FOR
24 HOUR SCRUB/TURNAROUND OPERATIONS

PERFORM ET TPS ICE/FROST & DEBRIS
EVALUATION

ET READY FOR LOX & LH2 LOADING

VERIFY NO INCREASE ABOVE BASELINE FOR
H2 CONCENTRATION PRIOR TO START OF LOX/LH2
LOADING IN THE FOLLOWING LOCATIONS:
ORBITER PAYLOAD BAY
ORBITER LOWER MID BODY
ORBITER AFT FUSELAGE

ORBITER READY FOR LOX & LH2 LOAD

PROCEED WITH LOX & LH2 LOAD

INITIATE LOX TRANSFER LINE CHILLDOWN
INITIATE LH2 TRANSFER LINE CHILLDOWN

PERFORM OMS PROP TANK REPRESSURIZATION

VERIFY SRB NOZZLE FLEX BEARING & SRB NOZZLE
TO CASE JOINT TEMPERATURE REQUIREMENTS
ACTIVATE LCC MONITORING SOFTWARE
12/02/98   7:19:00 PM T - 000/05:50:00 LH2 FACILITY & ORBITER CHILLDOWN COMPLETE. INITIATE ORBITER MPS CHILLDOWN
INITIATE LH2 SLOW FILL TO 5% SENSORS WET
LOX TRANSFER LINE CHILLDOWN COMPLETE
12/02/98   7:47:00 PM T - 000/05:22:00 PERFORM IMU PREFLIGHT CALIBRATION
12/02/98   7:49:00 PM T - 000/05:20:00 ORBITER MPS CHILLDOWN COMPLETE. INITIATE
LOX SLOW FILL.
12/02/98   7:54:00 PM T - 000/05:15:00 LH2 ENGINE CUT OFF SENSORS WET
12/02/98   7:59:00 PM T - 000/05:10:00 LOX TRANSITION TO FAST FILL COMPLETE.
NOW IN FAST FILL TO 98%
12/02/98   8:09:00 PM T - 000/05:00:00 ET LH2 5% SENSOR WET.

INITIATE LH2 FAST FILL TO 98%
MPS LH2 RECIRC PUMPS ACTIVATED
MONITOR AFT FUSELAGE AND ET INTERTANK FOR ANY H2 CHANGE
12/02/98   8:29:00 PM T - 000/04:40:00 MPS LH2 RECIRC PUMP ACTIVATION COMPLETE
12/02/98   9:09:00 PM T - 000/04:00:00 PERFORM MILA ANTENNA ALIGNMENT
PERFORM LH2 ET ULLAGE PRESSURE TRANSDUCER
NUMBER 4 VERIFICATION
12/02/98   9:24:00 PM T - 000/03:45:00 LH2 98% SENSOR IS WET. INITIATE TOPPING
TO 100%.
ET BIPOD HEATERS ARE ACTIVATED
PERFORM ORBITER/GSE PIC RESISTANCE TEST

PERFORM SRB/ET PIC RESISTANCE TEST

ASSEMBLE ICE CREW & CLOSEOUT CREW FOR
PAD ENTRY
12/02/98   9:39:00 PM T - 000/03:30:00 SWITCH TO MILA SECONDARY ANTENNA & PROCEED
WITH ALIGNMENT
12/02/98   9:59:00 PM T - 000/03:10:00 *************************************
* THE COUNTDOWN CLOCK WILL HOLD AT *
* T-03H00M *
*************************************
12/02/98   10:04:00 PM T - 000/03:05:00 LH2 TOPPING IS COMPLETE
INITIATE REPLENISH
LOX IN STABLE REPLENISH
LH2 IN STABLE REPLENISH
12/02/98   10:09:00 PM T - 000/03:00:00 THE COUNTDOWN CLOCK IS HOLDING AT T-03H00M. MILA ANTENNA ALIGNMENT COMPLETE
RESET ORBITER VENT DOOR COMMANDS
PERFORM T-3 HR SNAPSHOT ON FLIGHT CRITICAL
& PAYLOAD MDMSMILA ANTENNA ALIGNMENT COMPLETE
RESET ORBITER VENT DOOR COMMANDS
PERFORM T-3 HR SNAPSHOT ON FLIGHT CRITICAL
& PAYLOAD MDMS


**************************************
*THE NEXT PLANNED HOLD IS AT T-20M00S*
**************************************
ICE TEAM READY FOR PAD ENTRY
CLEAR ICE TEAM & CLOSEOUT CREW TO PAD

PERFORM ICE/DEBRIS INSPECTION
INGRESS ORBITER CREW COMPARTMENT

GO FOR FLIGHT CREW WAKE UP
PERFORM COMM CHECKS
ALL ORB TEST TEAM SWITCH TO CHNL 212
CONFIGURE & INSPECT CREW MODULE FOR CREW
INGRESS
PERFORM POTABLE SUPPLY WATER ADJUST
PERFORM IMU PRE-FLIGHT CALIBRATION
PERFORM ER OPEN LOOP CHECKS



ER OPEN LOOP CHECK COMPLETE

VERIFY 4 HR 15 MIN JIMSPHERE HAS BEEN
RELEASED

PERFORM FLIGHT CREW WEATHER BRIEFING

INSTALL LIOH CANISTERS
POWER UP SRB TRACKING
SYSTEM
12/03/98   12:09:00 AM T - 000/03:00:00 THE COUNT HAS RESUMED
************************************
* NOTE: THE NEXT PLANNED HOLD IS *
* AT T-20 MINUTES *
************************************
ICE/DEBRIS INSPECTION COMPLETE
PRESSURIZE MPS HELIUM TANKS
MONITOR PAYLOAD BAY & MIDBODY DURING
HELIUM TANK PRESS
PERFORM SRB RGA POWER UP & TORQUE TEST
ACTIVATE SRB RGA LCC EXCEPTION
MONITORING
12/03/98   12:14:00 AM T - 000/02:55:00 FLIGHT CREW DEPART O&C BUILDING TO PAD
IDENTIFY ANY COLLISION AVOIDANCE
TIMES FOR THIS LAUNCH WINDOW OR
LAUNCH PERIOD
12/03/98   12:24:00 AM T - 000/02:45:00 ICE DEBRIS REPORT
VERIFY NO VIOLATION OF LAUNCH COMMIT
CRITERIA
12/03/98   12:29:00 AM T - 000/02:40:00 VERIFY TLA
12/03/98   12:39:00 AM T - 000/02:30:00 SWITCH STANDBY FRONT END PROCESSORS TO RF
MPS HELIUM TANK PRESSURIZATION IS COMPLETE
PERFORM ET LIQUID LEVEL SENSOR CHECKS
PERFORM SRB MDM COUNTDOWN VERIFICATION
INGRESS FLIGHT CREW & SEATS
12/03/98   12:54:00 AM T - 000/02:15:00 ET LIQUID LEVEL SENSOR CHECKS COMPLETE
12/03/98   12:59:00 AM T - 000/02:10:00 PERFORM POST INGRESS SWITCH RECONFIGURATION
12/03/98   1:09:00 AM T - 000/02:00:00 PERFORM GLS INITIALIZATION
REPORT STATUS IN RETRIEVAL AREA
ACTIVATE SRB HPU GAS GENERATOR HEATERS
12/03/98   1:14:00 AM T - 000/01:55:00 PERFORM FIRST MOTION SIMULATED SIGNAL TEST
12/03/98   1:19:00 AM T - 000/01:50:00 PERFORM ETR SRSS VERIFICATION TEST
12/03/98   1:34:00 AM T - 000/01:35:00 VERIFY ALL SYSTEMS READY FOR CREW MODULE
CLOSEOUT
12/03/98   1:39:00 AM T - 000/01:30:00 PERFORM AIR TO GROUND VOICE CHECKS
PERFORM SRM CHAMBER PRESSURE VERIFICATION
12/03/98   1:49:00 AM T - 000/01:20:00 **************************************
* COUNTDOWN CONTINGENCY HOLD POINT *
**************************************
THE COUNTDOWN CLOCK WILL HOLD
CLOSEOUT CREW COMPARTMENT HATCH
PERFORM ER OPEN LOOP AUTOMATIC COMMAND
CARRIER CONTROL VALIDATION TESTS
12/03/98   1:59:00 AM T - 000/01:10:00 PERFORM ETR HOLDFIRE CHECKS
PERFORM FINAL COLLISION AVOIDANCE UPDATE
PERFORM CABIN LEAK CHECK
12/03/98   2:09:00 AM T - 000/01:00:00 SRM CHAMBER PRESSURE VERIFICATION
IS COMPLETE
********************************
* NOTE: TIME CHANGE TO MINUTES *
* AND SECONDS *
********************************
12/03/98   2:14:00 AM T - 000/00:55:00 ACTIVATION
12/03/98   2:19:00 AM T - 000/00:50:00 PERFORM TERMINAL COUNT SRSS CLOSED LOOP
TEST
12/03/98   2:24:00 AM T - 000/00:45:00 PERFORM GLS MAINLINE ACTIVATION
PERFORM ORB/SRB LDB REDUNDANCY CHECKS
12/03/98   2:29:00 AM T - 000/00:40:00 GLS PRESEQUENCING HAS STARTED
FINAL CABIN LEAK CHECKS COMPLETE
PERFORM CABIN VENT
12/03/98   2:37:00 AM T - 000/00:32:00 PERFORM PASS/BFS TRANSFER PREPARATION
12/03/98   2:39:00 AM T - 000/00:30:00 PERFORM OMS GN2 PRESSURIZATION
12/03/98   2:40:00 AM T - 000/00:29:00 PERFORM MAIN ENGINE CONTROLLER PREFLIGHT
BITE CHECK
12/03/98   2:47:00 AM T - 000/00:22:00 PERFORM PASS-BFS TRANSFER
*****************************************
* THE COUNTDOWN CLOCK WILL HOLD AT T-20 *
*****************************************
CLOSE CABIN VENT VALVES
12/03/98   2:49:00 AM T - 000/00:20:00 CLEAR CLOSEOUT CREW FROM PAD. THE COUNTDOWN CLOCK IS HOLDING AT T-20
MINUTES FOR A PLANNED HOLD OF 10 MINUTES
REPORT HOLD TIME CONSTRAINTS
REPORT LOX DRAINBACK HOLD TIME
VERIFY CONSOLE PROGRAMS
20 MINUTE RECYCLE ENTRY
ALL TEST TEAM PERSONNEL SWITCH TO CHNL 212
VERIFY STATUS OF LANDING SITES
T-20 MIN BRIEFING:
LAUNCH WINDOW OPENS.
LAUNCH WINDOW CLOSES.
COLLISON AVOIDANCE (COLA) TIME FRAMES
L0x DRAIN BACK
IMU PREFLIGHT ALIGNMENT IS COMPLETE.
READY FOR TRANSITION TO OPS 1
ACTIVATE GNC PROFILE MONITOR
****************************************
* NOTE: AFTER T-20 MINUTES, ALL PROB- *
* LEMS OR TRENDS THAT REQUIRE A CDC *
* HOLD WILL BE REPORTED TO THE NTD ON *
* CHANNEL 212 TOGETHER WITH RECOMMEN- *
* DATION. AFTER T-5 MIN., ANY HOLD *
* MANUAL OR GLS, SHOULD BE ACCOMPANIED *
* BY A DESCRIPTION OF THE PROBLEM AND *
* A RECOMMENDATION. THE COUNT CLOCK *
* WILL CONTINUE UNTIL T-31 SEC UNLESS *
* THE RECOMMENDATION TO HOLD AT THE *
* NEXT MILESTONE IS NECESSARY. *
****************************************
GLS MILESTONES:
T-09M00S - GLS SEQ START
T-07M30S - OAA RETRACT
T-05M00S - APU START
T-04M00S - PURGE SEQ 4
T-02M55S - LOX PRESSURIZATION
T-01M57S - LH2 TERM REPLENISH
T-00M31S - GLS GO FOR GPC AUTO SEQ
*************************************
* AT T-9 MINUTES WHEN A "GO" IS *
* GIVEN, IT INDICATES THAT THE *
* REPORTING ELEMENT IS FREE OF PROB-*
* LEMS WHICH COULD PREVENT A SUC- *
* CESSFUL LAUNCH. IF A HOLD COMMAND*
* IS REQUESTED AND ISSUED BETWEEN *
* T-9 MINUTES AND T-31 SECONDS, THE *
* COUNTDOWN CLOCK WILL BE RESTARTED *
* UPON SUCCESSFUL RESOLUTION OF THE *
* PROBLEM WITHOUT A "GO" SURVEY *
* MADE OF ALL ELEMENTS. AFTER T-31 *
* SECONDS, ONLY CUTOFF IS AVAILABLE,*
* AND WILL RESULT IN A RECYCLE TO *
* T-20 MINUTES. FOR A CUTOFF, *
* PROWORDS "CGLS GIVE CUTOFF" WILL *
* BE USED. *
*************************************
****************************
* NOTE: THE NEXT HOLD WILL *
* BE AT T-9 MINUTES *
****************************
PERFORM FUEL CELL PURGE
OPS TRANSITION IS COMPLETE
12/03/98   2:59:00 AM T - 000/00:20:00 THE COUNTDOWN HAS RESUMED
12/03/98   3:00:30 AM T - 000/00:18:30 BACKUP FLT SYSTEM TO OPS 1 TRANSITION
IS COMPLETE
12/03/98   3:01:00 AM T - 000/00:18:00 PERFORM T-20 MINUTE GPC DUMP
12/03/98   3:03:00 AM T - 000/00:16:00 PERFORM BACKUP FLT SYSTEM PREFLIGHT
UPLINK LOADING
VERIFY WATER SPRAY BOILER QUANTITY
PERFORM MPS HELIUM RECONFIGURATION
12/03/98   3:04:00 AM T - 000/00:15:00 OMS/RCS CROSSFEED VALVES CONFIGURED
FOR FLIGHT
INITIATE SRB AFT SKIRT GN2 PURGE HIGH
FLOW RATE FOR LEFT & RIGHT SRBs
12/03/98   3:06:00 AM T - 000/00:13:00 FUEL CELL PURGE IS COMPLETE
ADJUST FUEL CELL LOADS
12/03/98   3:07:00 AM T - 000/00:12:00 T-20 MINUTE GPC DUMP IS COMPLETE
THE COUNTDOWN CLOCK WILL HOLD AT
T-9 MINUTES
12/03/98   3:09:30 AM T - 000/00:09:30 VERIFY SRB HPU LEVELS
REDUCE PAYLOAD BAY PURGE FLOWRATE
IF GREATER THAN 180 LBS/MIN
NTD LAUNCH READINESS POLL OF
SHUTTLE LAUNCH TEAM
PERFORM NSTS OPERATIONS MANAGER'S
LAUNCH READINESS CHECK
VERIFY CAPE WEATHER FORECASTS MEETS LAUNCH
WEATHER CRITERIA
PERFORM HGDS & BACKUP HGDS AUTO
CALIBRATION
REMOVE SRB IGNITER HEATER POWER
12/03/98   3:10:00 AM T - 000/00:09:00 THE COUNTDOWN CLOCK IS HOLDING AT T-9 MINUTES
12/03/98   3:50:00 AM T - 000/00:09:00 THE COUNT HAS RESUMED
GLS AUTO SEQUENCE HAS BEEN INITIATED
SELECT PAYLOAD BAY SAMPLE LINE
12/03/98   3:51:30 AM T - 000/00:07:30 RETRACT ORBITER ACCESS ARM
12/03/98   3:52:00 AM T - 000/00:07:00 SELECT MIDBODY SAMPLE LINE
12/03/98   3:52:45 AM T - 000/00:06:15 PERFORM APU PRE-START
SELECT ET INTERTANK SAMPLE LINE
12/03/98   3:54:00 AM T - 000/00:05:00 GO FOR APU START
12/03/98   3:54:05 AM T - 000/00:04:55 VERIFY ET/SRB & ARM DEVICE ARMED
VERIFY SRM IGNITION SAFING & ARM DEVICE
ARMED
TERMINATE LOX REPLENISH
12/03/98   3:54:12 AM T - 000/00:04:48 CLOSE LOX INBOARD F&D VALVE
12/03/98   3:54:25 AM T - 000/00:04:35 OPEN LOX DRAIN VALVE
12/03/98   3:54:30 AM T - 000/00:04:30 MAIN FUEL VALVE HEATERS OFF
12/03/98   3:55:00 AM T - 000/00:04:00 INITIATE SSME PURGE SEQUENCE 4
VERIFY SSME VALVE MOVEMENT IN THE
CLOSE DIRECTION
12/03/98   3:55:05 AM T - 000/00:03:55 INITIATE ORBITER AERO SURFACES PROFILE
CHECK
12/03/98   3:55:30 AM T - 000/00:03:30 INITIATE MPS GIMBAL PROFILE CHECKS
12/03/98   3:55:57 AM T - 000/00:03:03 MPS ENGINES TO START POSITION
VERIFY BODY FLAP TO LAUNCH POSITION
12/03/98   3:56:00 AM T - 000/00:03:00 SELECT AFT FUSELAGE SAMPLE LINE
12/03/98   3:56:05 AM T - 000/00:02:55 INITIATE ET LOX PRESSURIZATION
TERMINATE SSME GN2 PURGE
12/03/98   3:56:10 AM T - 000/00:02:50 TERMINATE GOX WENT HOOD PURGE
RETRACT GOX VENT HOOD
12/03/98   3:56:25 AM T - 000/00:02:35 PRSD TRANSFER TO INTERNAL REACTANTS
12/03/98   3:57:00 AM T - 000/00:02:00 CLOSE VISORS
12/03/98   3:57:03 AM T - 000/00:01:57 TERMINATE LH2 REPLENISH
CLOSE LH2 TOPPING VALVE
CLOSE LH2 VENT VALVE
12/03/98   3:57:14 AM T - 000/00:01:46 INITIATE LH2 PREPRESS
12/03/98   3:57:30 AM T - 000/00:01:30 T-1 MINUTE 30 SECONDS
ET BIPOD HEATERS OFF
12/03/98   3:58:00 AM T - 000/00:01:00 T-1 MINUTE
12/03/98   3:58:05 AM T - 000/00:00:55 PERFORM SRB FWD MDM LOCKOUT
VERIFY SRB MDM CRITICAL COMMANDS
12/03/98   3:58:10 AM T - 000/00:00:50 GROUND POWER REMOVAL
12/03/98   3:58:12 AM T - 000/00:00:48 CLOSE LOX & LH2 OUTBOARD FILL & DRAIN
VALVES
DEACTIVATE SRB JOINT HEATERS
12/03/98   3:58:29 AM T - 000/00:00:31 GLS GO FOR AUTO SEQUENCE

ARM CUT OFF
INITIATE RSL5
**************************************
* NOTE: AFTER THIS TIME, ONLY CUT *
* OFF IS AVAILABLE & WILL RESULT IN *
* GLS RECYCLING TO T-20 MINUTES & *
* HOLDING *
***************************************
ORB VENT DOOR SE9 START
12/03/98   3:58:32 AM T - 000/00:00:28 START SRB APU'S
12/03/98   3:58:34 AM T - 000/00:00:26 START SRB APU'S
12/03/98   3:58:35 AM T - 000/00:00:25 25 SECONDS
12/03/98   3:58:39 AM T - 000/00:00:21 START SRB GIMBAL TEST
12/03/98   3:58:40 AM T - 000/00:00:20 20 SECONDS
12/03/98   3:58:44 AM T - 000/00:00:16 ACTIVATE SOUND SUPPRESSION WATER
12/03/98   3:58:45 AM T - 000/00:00:15 15 SECONDS
12/03/98   3:58:47 AM T - 000/00:00:13 PERFORM SRB AFT MDMS LOCKOUT
VERIFY LH2 HIGH POINT BLEED VALVE CLOSED
TERMINATE MPS HELIUM FILL
12/03/98   3:58:50 AM T - 000/00:00:10 10 SECONDS

FREE HYDROGEN BURN OFF SYSTEM IGNITION
GLS GO FOR MAIN ENGINE START

REMOVE ET/SRB RANGE SAFETY INHIBITS
12/03/98   3:58:54 AM T - 000/00:00:06.48 MAIN ENGINE 3 START COMMAND
12/03/98   3:58:54 AM T - 000/00:00:06.36 MAIN ENGINE 2 START COMMAND
12/03/98   3:58:54 AM T - 000/00:00:06.06 MAIN ENGINE 1 START COMMAND
12/03/98   3:59:00 AM T - 000/00:00:00 T-ZERO SRB IGNITION
SRB HOLDDOWN RELEASE COMMAND
LIFTOFF